Almost 80GW of battery storage has planning consent but is not yet built, government database shows

The October 2026 Renewable Energy Planning Database lists almost 80GW of battery storage with consent but not yet built, against under 6GW operating.

Close-up of electrical transformers with colorful tops and wires in an outdoor setting.

The government’s latest Renewable Energy Planning Database (REPD), published on 13 November 2026, lists almost 80 GW of battery storage projects in the UK that have planning permission but have not started construction. By our own calculation from the October 2026 extract, that compares with about 10.6 GW of batteries under construction and about 5.8 GW already operating.

The REPD tracks renewable electricity and storage projects above 150 kW from planning application through to operation. All figures below are our own totals from the published file, based on the capacity recorded for each project.

The wider pipeline

Across all technologies, the database records about 155 GW of consented projects awaiting construction, against about 59 GW of operational capacity. Batteries make up the largest share of that waiting list, ahead of offshore wind at about 29 GW and solar at about 29 GW.

A further 37 GW of battery storage is still at the planning application stage, according to our count.

Most of the consented battery capacity is recent. Projects consented in 2025 account for about 38 GW, and those consented so far in 2026 for about 15 GW. By location, roughly 54 GW is in England and 21 GW in Scotland, with the rest in Wales and Northern Ireland.

Why so much is waiting

Planning permission is only one step. A battery energy storage system also needs a grid connection date and a viable business case before it can be built, and many consented schemes will never go ahead. The government says it is reforming the grid connection queue so that projects that are ready and needed connect first. The latest stage of that process is covered in our report on Gate 2 connection offers.

The database also has limits. It relies on planning records and developer information, so status changes can appear with a delay, and a project’s recorded capacity may change before it is built.

What it means for the energy system

Batteries store cheap electricity, often from wind and solar, and release it when demand is high, which reduces the need for gas-fired generation at peak times. The government’s clean electrification roadmap, published a day earlier, restates an ambition for 51 to 66 GW of clean flexibility, including storage, interconnectors and demand shifting, by 2030.

The REPD figures suggest planning consent is not the main constraint on battery storage. How much of the consented pipeline is actually built will depend largely on how grid connection reform plays out over the next few years.

Sources

Every figure in this article was checked against these primary sources (last checked 13 Nov 2026). Read our methodology.

  1. DESNZ: Renewable Energy Planning Database quarterly extract (October 2026 update, 13 November 2026)
  2. DESNZ: Renewable Energy Planning Database, October 2026 (CSV)
  3. DESNZ: The UK's clean electrification roadmap (12 November 2026)